Interport-Baytown Phase I & II
Performed the Heavy / Civil site work construction for Cadence McShane
- Site clearing & grubbing - 90 acres
- Earthwork cut & fill - 260,658 CY
- Imported select fill -101,240 CY
- Lime stabilized parking - 118,234 SY
- Lime stabilized phase - 2 building pad utilizing on site common fill placed in each 8 inch lifts - 324,450 SY
Exceeded the schedule beyond the General Contractors expectation!