Featured Articles


W. T. Byler Builds Upon Varied Site Prep Services


Houston-based civil sitework and railroad contractor W.T. Byler Co. has laid the groundwork to advance as one of the most formidable enterprises of its kind in Texas and southwestern Louisiana thanks to its diverse clientele, numerous site preparation services and a rigorous safety program. Revenue for the family-owned business, founded in 1974, rose nearly 70% to $420.29 million in the past year alone.

The open-shop firm engages in 60 to 80 projects a year, according to Wendell Rychlik, executive director of business development and marketing for Byler. In to addition to private design-build railroad projects, Byler's direct-hire workforce of up to 1,000 engages in a variety of services across numerous sectors, including clearing and grubbing, ground improvement earth surcharge, mass excavation and embankment, below-grade piping installation, in-situ and pulvimixing soil stabilization. Construction of site structures encompasses building pads, site-work concrete, asphalt paving, heavy haul roads, laydown yards, brine ponds and dredge material placement areas.

The firm has built hundreds of miles of rail work, including turnkey construction of Class 1 main 1 lines, storage-in-transit (SIT) yards, transload sidings, spurs and wye tracks, all executed among a variety of soil and environmental conditions. Byler also performs railroad maintenance-of-way and railroad emergency response.

View Full Article

Keeping Gulf Coast Industry on Track


In order to develop these rail-served industrial parks, including track construction and other infrastructure improvements for all these mega projects, WT Byler Co has been Rail Logix’s go-to delivery for both site and rail construction.

In working with Rail Logix, the schedule is driven by their needs. Concept drawings typically begin with 2D views that are transformed into 3D models with supporting infrastructure and drainage, in weeks not months. This requires working with various consultants, architects, railroads, pipelines and other agencies simultaneously during the initial design process and construction.

Jim Jackson, P.E., project executive with WT Byler Co explains, “We go from simple concept layouts to complete construction drawings at a very fast pace. Most times, construction must start early to maintain scheduled delivery date while we are still solving lagging items. For example, there may be pipelines and utilities crossings to be mitigated, rock within the subgrade to be removed or there are long lead time materials to procure. Additionally, client needs may require dock high capabilities, pit conveyor systems or other types of rail unloading structures.”

Currently, WT Byler Co has excavated more than 3 million cubic yards of earth materials, soil stabilized 50,000 tons of lime/cement and placed 1,000,000 tons of aggregate base materials to build a combination of over 100 miles of track, plus infrastructure, for Rail Logix’s four existing parks.

View Full Article

LyondellBasell PO/TBA June 2017: Site Clearing & Grubbing Has Begun!


Contractors have been busy cutting down trees, clearing underbrush, shredding grass, grinding, chipping, and hauling everything away. Other areas are waiting for permit approval from Harris County so they can begin the clearing of 100 acres.

“Progress at BLO is proceeding as per schedule. Clearing and grubbing is nearly finished for Phase I. Great communications between all relevant parties has helped with obtaining permits in a timely manner which in turn, allowed work to start smoothly and on time,” says Mike Crosby, LYB construction manager for the BLO site. “We have commenced with the underground survey scope of work with RadarView They look for obstacles, utilities or anything else underground using GPR (Ground Penetrating Radar), which might affect our engineering or design and may require us to make changes."

Robert Manalli is Fluor’s construction manager for the BLO site. “We have a team of contractors and workers that are excited and anxious to get the work moving,” says Robert. “Early in the game, the PO/TBA construction, LYB safety and operations teams met to review the scope of work in detail. We discussed safety plans and permits and everything else we could think of. We wanted to be sure all parties clearly understood their roles and responsibilities in these early stages.” Mike added, “We have crews for 3 sub-contractors, WT Byler, RadarView, and Tulunay-Wong Engineers on...

View Full Article

Build Houston June/July 2017 Cover Story: Setting the Standard


The phrase “practice makes perfect” has never been truer than when used to describe industry leader, W.T. Byler Co. as they celebrate the completion of one of their most recent projects – LACC Ethane Cracker Project in Lake Charles, Louisiana.

As announced in December of 2015, Axiall, a Westlake Company and Lotte Chemical Corp. is making a combined $3 billion capital investment with $1.9 billion invested in a new ethane cracker facility beside Axiall’s current Lake Charles manufacturing plants in Calcasieu Parish. Combined, the developments are expected to create 250 new direct jobs.

The project originally required a large quantity of select soil to be brought in from offsite. During the interview process, W.T. Byler Co. offered a value engineering alternative by making the select fill onsite. This not only saved the owner money, but also precious time. After the interviews, W. T. Byler Co. was award the project.

W.T. Byler Co.’s team of 135 personnel and 90 machines got to work to complete the 220-acre project in nine months. By project’s end, W.T. Byler Co. had manipulated over 35,000 tons of lime for soil stabilization, 22,000 tons of fly-ash used as a drying agent, moved 1.35 million cubic yards of earth materials to line and grade, installed turnkey underground piping systems and placed more than 550,000 tons of...

View Full Article